Our electricians assigned to this job put in a fantastic effort during the first week removing all of the old storage heating from the building as well as installing half of the new storage heating and yes that meant walking up and down the monument many many times with heater bricks.
Another couple of days this week of brick carrying and heater installation will see the bulk of the new heater work complete as we then move on to working alongside the shop fitting company installing the new exhibitions.